Community Criteria Definitions
- Placement Opportunities – Project Advisory Teams identified areas for the transmission
line that would be preferred by the communities. - Avoidance Areas – Project Advisory Teams identified areas that are important to the
communities. The communities recommend avoiding these areas when siting a route for
the transmission line.
- Existing energy corridors
- West Wide energy corridor
- Public land (federal and state)
- Along Interstate I-84
- Along property lines
- Outside city limits
- Exclusive Farm Use (EFU) land
- Irrigated farmland
- Aerial spraying activity areas
- Rangeland
- Scenic view sheds
- Areas that have potential for residential and/or business development
- Areas of tourism
- Historic landmarks
- Narrow valleys with agricultural operations
- Private resource land (i.e., timber)
- Sensitive wildlife areas (i.e., sage grouse leks)
- Water resources and wetlands
- Schools
- Private residences