Studying proposed generator interconnections has become a major burden for transmission providers, who are overwhelmed with requests for interconnection, many of which will never be built.
Information is from the Edison Electric Institute: http://www.eei.org/meetings/Meeting%20Documents/2008-0811Blackburn_presentation.pdf
Midwest ISO has 402 pending interconnection requests for 83,000 MW of generation, more than half its existing capacity.
When a generator drops out of the interconnection queue, it may affect the interconnection costs of lower-queued generators.FERC has signaled a willingness to consider alternatives to the sequential processing of interconnection requests.
The Energy Policy Act of 2005
- Greater transparency in planning transmission systems and evaluating requests for service.
- Greater flexibility in provision of transmission service over constrained facilities.
- Greater timeliness and accountability in studying system upgrades needed to provide transmission service.
- Greater stability and certainty of transmission requirements, resulting from requiring customers to give advance notice of whether they will renew their service at the end of their contract terms.
- Requires regional planning of transmission construction that is open and transparent to customers.
- Requires redispatch service: Customers who otherwise would be denied service can agree to take service and pay the cost of redispatching generation to unload congested lines and allow the customers’ energy to be transmitted.
- Requires conditional firm service: Customers who otherwise would be denied service can agree to take service subject to curtailment if specified conditions occur or for a specified number of hours per year.
- FERC has approved a number of proposals, but two of the five Commissioners advocate using much more stringent criteria that would result in denial of many incentive requests.
- Construction expense must represent a very substantial proportion of total utility cost.
- Utilities must demonstrate use of innovative technologies.
- Utilities must show that the incentives benefit customers, not shareholders.
- Granting some incentives (such as CWIP (Construction Works in Progress) in rate base) may result in reducing risk and therefore reduce the allowed return on equity. (Pre-approved Ratemaking.)
*from Lisa Rackner's latest epistle, "IDAHO POWER COMPANY'S RESPONSE TO STOP IDAHO POWER'S MOTION TO POSTPONE AND CONSOLDATE," which you can read free of charge at the Oregon PUC's LC-41 docket, http://apps.puc.state.or.us/edockets/docket.asp?DocketID=13697